Bangalore metro project work to begin from Sept

Our Bureau

To go before CCEA on March 16


Bids and deals
25 expressions of interest received for building elevators.
12 contractors would be shortlisted on March 20.
For main works, five of the nine consortia will be shortlisted.


The Namma Metro logo

Bangalore , March 14

With the use of standard gauge cleared, work on the Rs 6,300-crore Bangalore metro rail project is expected to begin in full swing by September this year.

The project is slated to go before the CCEA on March 16, Mr K.N. Shrivastava, Managing Director of Bangalore Metro Rail Corporation Ltd, told a news conference.

The empowered Group of Ministers had cleared the use of standard gauge (1.43 m) for the Bangalore's much-delayed public transport project.

The metro is promoted jointly by the State and the Centre.

FIs' offers

Mr Shrivastava said domestic FIs had made overwhelming offers totalling Rs 4,000 crore for the domestic debt component of Rs 1,200 crore.

"This puts us in a strong position during negotiations," he said.

For the rest, the metro will get Rs 1,500 crore from the Centre, Rs 1,800 crore from the State Government; Japan Bank for Investment & Cooperation (JBIC) will provide Rs 1,800 crore of the Rs 3,000-crore loan at 1.3 per cent.

The Union and the Japanese governments are slated to sign the debt agreement in Japan on March 27.

An infrastructure cess, being levied by Karnataka since 1995, has touched Rs 800 crore, half of which has been released.

Project duration

As per the present schedule, the full phase 1 will be 36.5 km long, to be built over five years. Seven km from Byappanahalli to the cricket stadium on East-West corridor would be taken up first and the first trains would run in three years.

A comprehensive transport and traffic study to be out in November is to determine the next course and continuation of the cess.

Twelve contractors would be shortlisted on March 20 out of the 25 expressions of interest received for building elevators.

For the main works, five of the nine consortia will be shortlisted after the general consultants are appointed by May-end, with the approval of the JBfor IC.

Pending the CCEA clearance and the State Cabinet's approval to transfer 57 acres of land from its various entities, nearly all the decks have been cleared, Mr Shrivastava said.

Twenty seven acres of private land is needed and the corporation would soon begin measuring and documenting the 621 structures on these spaces.

Most of the land has come in, including the 102 acres of Defence land and 26 acres from NPCIL.

More Stories on : Railways | Karnataka | Infrastructure

Article E-Mail :: Comment :: Syndication :: Printer Friendly Page



Stories in this Section
Tripartite panel on airport revamp yet to meet


Manugistics tool for Continental
Encouraging signals
Steamer agents body bid to bring back ICD cargo to Kochi
Hyundai Merchant plans to link China
AP Govt to introduce Maritime Board Bill
Essar Shipping takes delivery of VLCC
TNT scouting for acquisitions in India
`World class'
Bangalore metro project work to begin from Sept
TCI plans Rs 300 cr for expansion
Insurance scheme for Mumbai CNG users



The Hindu Group: Home | About Us | Copyright | Archives | Contacts | Subscription
Group Sites: The Hindu | Business Line | Sportstar | Frontline | The Hindu eBooks | The Hindu Images | Home |

Copyright © 2006, The Hindu Business Line. Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu Business Line