Tiroda project: Adani Power renegotiates equipment cost

Riding on commodity price meltdown.


The company had recently renegotiated the Boiler, Turbine and Generator (‘BTG’) package with Chinese contractor Sichuan Machinery.


Pratim Ranjan Bose

Kolkata, Jan. 12In an effort to take advantage of the meltdown in commodity prices, Adani Power Ltd (APL) seems to have renegotiated the cost of critical equipment with the Chinese contractor for its super critical coal-based 1,980-MW (3X660 MW) power project at Tiroda in Gondia district in Maharashtra. The project is being executed by Adani Power Maharashtra, a wholly owned subsidiary of APL.

Though the Adani group declined to comment, industry sources close to the development told Business Line that the company recently renegotiated the Boiler, Turbine and Generator (‘BTG’) package with Sichuan Machinery and Equipment Import and Export Co Ltd.

According to sources, the renegotiated contract may reduce the project cost by up to 10 per cent, which is expected to a reduction of over Rs 800 crore.

IPO

Adani Power, a subsidiary of Adani Enterprises, had filed a draft red herring prospectus to raise over Rs 5,600 crore through an IPO. According to the prospectus, the company was allocated two coal blocks at Lohara West and Lohara Extension for Tiroda. The project is expected to be fully commissioned by April 2012.

Though SEBI cleared the proposal in September this year, the IPO plan was postponed in view of market conditions.

Overall, APL proposed to set up six coal-based thermal power projects in Gujarat, Maharashtra and Rajasthan totalling 9,900 MW at an estimated investment of Rs 43,139 crore by 2011-2012.

Mundra project

Of the six projects, the 4,620-MW coal-based Mundra power project is in advanced stage of implementation. Phase-I (660 MW) of the project, including two units of 330 MW, may come on stream in February. Work is also nearing completion for Phase-II (660 MW).

Construction of phase III (2X660 MW) and IV (3X 660 MW) is underway. The entire project is expected to be commissioned latest by 2011.

Mundra power project is located in the Mundra Port and SEZ area, also promoted by Adani Group. The critical equipment for the project is also sourced from Chinese contractors.

Related Stories:
Adanis will supply Mundra power to Gujarat, Haryana

More Stories on : Outlook | Power | Electrical Goods

Article E-Mail :: Comment :: Syndication :: Printer Friendly Page




Stories in this Section
DLF repays loans of about Rs 1,000 cr


Rajasthan crude similar to Indonesian varieties, says Cairn
ICAI plans to tighten rules on auditors’ tenure
Satyam effect: ICAI decides on deterrent action against CA firms
RIL may be allowed to sell gas to third parties
More banks set to tap bond market to raise capital
ONGC Videsh to pay Imperial shareholders today
Satyam’s ex-CFO: Auditors did not point out any deficiencies
Satyam to scout for new CEO, CFO from within or outside
HCC to build Rs 40,000-cr ‘water front city’ in Gujarat
Maxcor Lifescience in pact with Micell
Tiroda project: Adani Power renegotiates equipment cost
Bajaj redrafts bike strategy, to launch XCD 135 on Jan 21
Gas production from KG fields expected by Feb-end: RIL
IOC expects gross refining margin at $4-5 a barrel




Life



The Hindu Group: Home | About Us | Copyright | Archives | Contacts | Subscription
Group Sites: The Hindu | The Hindu ePaper | Business Line | Business Line ePaper | Sportstar | Frontline | The Hindu eBooks | The Hindu Images | Home |

Copyright © 2009, The Hindu Business Line. Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu Business Line