Uncertainty over Tadri ultra mega power project

C. Shivkumar
Anil Sasi

Mounting opposition from environmentalists, Navy

Bangalore/New Delhi , May 25

Confronted with mounting opposition from environmentalists and reservations from the Indian Navy, the proposed 4,000-MW Tadri ultra mega power project is faced with uncertainty.

Opposition from the greens stemmed from concerns over potential damage to the Aghnashini Estuary in the region recognised as one of the world's environmental hotspots.

The Navy's reservations on the power project site were in view of Tadri's proximity to the Western Naval Command's base in Karwar, Project Seabird.

Tadri is about 40 km south of Karwar, where the naval base is still under construction. Moreover, NPCL's Kaiga nuclear power plant is also in the vicinity.

Expressions of interest floated for the project a month ago saw as many as 20 applicants.

These included power sector biggies led by NTPC Ltd, Larsen & Toubro, Reliance Energy and Tata Power.

Others in the fray include Sterlite Industries Ltd, Tata Power, Aditya Birla Group, Gammon India, Madhucon, Videocon Industries Ltd, Ashok Leyland, Essar Power, Torrent Power, Sumitomo, Itochu, Lanco Infratech Ltd, Navbharat Ferro Alloys Ltd, Khanjee Holdings, KSK Electricity Financing India Pvt Ltd, BSCPL-SCL-CR18G consortium and the BSCPL-SCL joint venture.

The concerted opposition has triggered moves to find alternative locations in Karnataka.

Alternative location

One option, the sources said, was to locate the project in Mangalore.

This was in the vicinity of the Mangalore Port Trust and the site that was originally allocated to Cogentrix/China Light & Power for their 1000 MW project. In this location Karnataka Industrial Areas Development Board possesses about 1000 acres of land, sources said.

Besides, both CLP Power and Cogentrix had obtained clearance from the CEA and the Ministry of Environment for setting up the project, before pulling out for want of a counter guarantee from the Centre.

However, Karnataka's Principal Energy Secretary, Mr Dilip Rau, said that it was too early to decide on any relocation of Tadri.

He said, "Any such decision can be taken only after the Environmental Impact Study is made and the State Pollution Control Board makes an assessment."

The project is still in the incipient stages and a detailed project report would have to be prepared by the special purpose company that would be formed for the project.

Tadri is already a minor port. However Mr Rau said, "The port channel would require major dredging for ensuring passage of large bulk carriers."

The proposed ultra mega project's feedstock requirement was estimated at close to 15 million tonnes of low ash coal with a calorific value of 6,000 kilo calories per kg. This was expected to be sourced from Australia or Indonesia.

The uncertainty over the project comes as blow to the Centre. Already the Centre has initiated the process of moving another ultra mega project proposed in Chhattisgarh to a location outside the State.

This comes in the wake of claims made by the Chhattisgarh administration to 12 per cent free power entitlement from the project and a total allocation of generation worth 3,500 MW out of the 4,000 MW-capacity of the project.

More Stories on : Power | Security | Environment | Karnataka

Article E-Mail :: Comment :: Syndication :: Printer Friendly Page



Stories in this Section
Online platform for recruiters, companies


Maharashtra steps to prevent flood
Monsoon onset over Kerala, North-east likely tomorrow
L&T making enquiries to import cement
Mobile revelation
Why the SEZ policy needs a re-think
Decision likely on petro price revision next week
OVL signs production sharing contracts with PetroVietnam
Focus Energy discovers gas in Rajasthan
New MRP label on drugs mandatory from July
`Tie-up with life sciences cos holds the key'
Uncertainty over Tadri ultra mega power project
Expedite gas procurement, NTPC told
States to seek higher share of VAT pie
Separate credit plan for SMEs in AP chalked out
Improving human capital — A role for Corporate India
CII-UK exam centre in Hyderabad
`Attract CTV facility in Nanguneri park'
ENT research institute in Kochi
ENT research institute in Kochi
Noida expressway: `Land auction was transparent'
Bt cotton pricing puts farmers in a spot
Expert proposes enterprise development panel
Interactive session on US visas
KINFRA to organise lecture
B-school's conference on May 27
Entrepreneur development programme
Wheat arrivals rise as prices begin to decline
World coffee output, exports decline
`Super Basmati' eligible for exports



The Hindu Group: Home | About Us | Copyright | Archives | Contacts | Subscription
Group Sites: The Hindu | Business Line | Sportstar | Frontline | The Hindu eBooks | The Hindu Images | Home |

Copyright © 2006, The Hindu Business Line. Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu Business Line