Expressway project: Karnataka mulls annulling agreement

S. Rajendran

Apex court may hear case in July


In a nutshell
PWD asked to be ready to complete the project
State Govt tired of a delay of nearly 12 years
2 important files on the project tracked down

Bangalore June 14 The Karnataka Government is likely to nullify the contract with the Nandi Infrastructure Corridor Enterprise (NICE), which is implementing the Bangalore-Mysore expressway project. Any decision of the Government will, however, be subject to the directions of the Supreme Court before which there are several petitions pertaining to the subject.

High-level sources in the Government told The Hindu here on Thursday that the Government was tired of the delay of nearly 12 years in the execution of the project, which is mired in litigation. The State Public Works Department has been asked to get ready to step in, if need be, and complete the project within two years.

The Government has filed an interlocutory application before the Supreme Court seeking the modification of an earlier order of the court in relation to the expressway project. The Supreme Court has been informed that the Government has tracked down two important files relating to the project.

Suppression of files

"The suppression of the files along with fabrication of records by a group of officials has resulted in the Supreme Court issuing certain directions to the Government. Now that the files have been traced, the Government has sought a modification of the order," said the source.

The interlocutory application is likely to be heard by the Supreme Court in the last week of July.

Talks

The Karnataka Chief Minister, Mr H.D. Kumaraswamy, has held several rounds of discussions with senior officials of the Public Works Department to undertake the expressway project, if the need arises. The Government would require at least Rs 5,000 crore to execute the project on the same standards prescribed for NICE.

The Chief Minister is also holding discussions with Law Department officials and legal experts on the course of action following nullification of the contract with NICE. The Government, if accused of violating the contract, may be dragged into arbitration proceedings by NICE.

Under the framework agreement, arbitration proceedings are to be held in London.

The sources said the Government is thinking of calling off the agreement with NICE after the recent seizure of two important files relating to the implementation of the project that had been "suppressed by some of the officials of the State". Hence, the Government has sought the Supreme Court's permission to carry out a preliminary fact-finding inquiry into how 2,289 acres of land over and above what was stipulated in the framework agreement was made over to NICE.

Files

The two files are the KIADB (Karnataka Industrial Areas Development Board) file number 1,256 pertaining to the expressway project, and PWD (Public Works Department) file number 155 CRM/95/Government land/99-2000 (2001).

The Government has sought action against the officials who allegedly suppressed the files and fabricated records. In the petition to the Supreme Court, an official, a former Public Works Department Secretary Major, has been identified as having allegedly colluded with NICE. It has also alleged that such officials on superannuation are now associated with the project company and even the children of some of them have benefited.

It has sought permission to continue with the B.C. Patel Commission of Inquiry (relating to the expressway project). The functioning of the commission (it took charge on July 18, 2006) was suspended following a submission made to the court by the Government. It was constituted to assess the quantum of loss, if any, to the Government and to the public both in terms of land and money, suggest remedial measures to undo such irregularities, fix responsibility and initiate action against officers, Ministers and others for acts of omission and commission, if any.

More Stories on : Infrastructure | Roadways | Courts/Legal Issues | Karnataka

Article E-Mail :: Comment :: Syndication :: Printer Friendly Page



Hiring

Stories in this Section
Mobile operators go for biofuel to power base stations


ABN Amro plans fund with Chindia flavour
Indian strike called off; full schedule from today
Tighter norms for domestic airlines' global flights likely
Wipro unveils `green' PCs
Expressway project: Karnataka mulls annulling agreement
OIL may dilute stake in KG onshore block
Core sector set to ride power addition
Kharif coverage trails in cereals, maize, oilseeds
ICICI Bank housing loan growth slows to 20%
Public sector insurers firm on capital raising plan
Crisil, ICRA up on IPO rating hopes
Dabur India up on acquisition talk
ICICI Bank issue: Sops to retail investors
IDBI raising $1.5 b thru medium term notes
ISPs say spectrum allocation favours mobile operators


The Hindu Group: Home | About Us | Copyright | Archives | Contacts | Subscription
Group Sites: The Hindu | The Hindu ePaper | Business Line | Business Line ePaper | Sportstar | Frontline | The Hindu eBooks | The Hindu Images | Home |

Copyright © 2007, The Hindu Business Line. Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu Business Line