IOC may commission Paradip-Haldia pipeline project by December

Monsoon delays work; expects to restart in October

Pratim Ranjan Bose

Kolkata, Aug. 18 IndianOil has now set a December 2007 deadline for implementing the Rs 1,200-crore Paradip-Haldia crude pipeline.

The pipeline — coupled with single point mooring (SPM) and storage facility at Paradip in Orissa — was originally scheduled for completion in March 2006.

Since the project would reduce the transportation cost of crude for both Haldia and Barauni refineries, IOC is expected to benefit in terms of a higher refining margin in both, beginning the fourth quarter of this fiscal.

Haldia and Barauni refineries currently refine over six million tonnes (47.4 million barrels) of crude oil each annually.

A project is underway to ramp up the capacity of Haldia refinery to 7.5 mt. Refining margins of both refineries are expected to increase by over $1 a barrel after the pipeline is commissioned.

Hurdles faced

The project ran into rough weather from its start, following a series of problems involving project design, environmental clearance, and last but not the least, differences with the Iranian contractor deployed to complete the SPM and the connecting 20 km offshore pipeline.

Finally, the 330-km sub-surface pipeline from Paradip to Haldia was completed in April-May this year but work was far from over at the SPM end.

Accordingly, IOC replaced the SPM project contractor — Iranian Offshore Engineering and Construction Company (IOEC) — by Oil and Gas Engineering Systems of Australia. IOEC was accused of inordinate delay in completion of the project.

Further delay

According to sources, though the company expected the new contractor to complete the remaining work by July-August 2007, work could not proceed owing to heavy monsoons in Orissa.

“We are now expecting to restart work in October and commission the project by December,” a senior IOC official told Business Line, denying any legal complications with regard to the change of contractor.

He was, however, silent on the impact on the project cost because of the delay.

“It was impossible to complete the project as per the original schedule. We are now striving to complete the remaining part of the project,” the official said.

Related Stories:
Paradip project: IOC may start tendering process soon
IOC scouts for gas for internal use at Haldia unit
IOC's Paradip projects run into rough weather

More Stories on : Outlook | Petroleum

Article E-Mail :: Comment :: Syndication :: Printer Friendly Page



Stories in this Section
Sobha Developers to sign MoU for hi-tech city in Kochi


MRPL wins safety award
Shareholders approve Bajaj demerger
Essel Propack sets up unit in Uttarakhand
Steel expansion may need Rs 2.8-lakh-cr
Triveni signs pact with Chinese firm
All that you wanted to know about sub-prime crisis
LME tag for Hind Zinc’s lead
Revival of 17 Central PSUs awaits Govt approval
Centre may invoke Act to take over closed tea gardens
IOC may commission Paradip-Haldia pipeline project by December


The Hindu Group: Home | About Us | Copyright | Archives | Contacts | Subscription
Group Sites: The Hindu | The Hindu ePaper | Business Line | Business Line ePaper | Sportstar | Frontline | The Hindu eBooks | The Hindu Images | Home |

Copyright © 2007, The Hindu Business Line. Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu Business Line