Adani Green Energy Limited has commissioned a 325-megawatt wind energy plant in Dhar district of Madhya Pradesh.
With the commissioning of this plant, its operational generation capacity has increased to 6.1 gigawatt (GW), Adani Green Energy Limited (AGEL) said in a statement on Monday.
"Adani Wind Energy MP One Private Ltd (AWEMP1PL), a subsidiary of AGEL, has commissioned a 324.4 MW wind power plant in Dhar, Madhya Pradesh," it said.
The plant has two 25-year Power Purchase Agreements (PPAs) with Solar Energy Corporation of India (SECI), one for 274.4 MW energy and another for 50 MW power, at a tariff of ₹2.83 per kwh (kilowatt hour).
Related Stories
Adani Group to become most profitable cement manufacturer
Adani Group last week completed buyout of Swiss major Holcim's stake in the two firmsThe newly commissioned plant will be managed by the Adani Group's 'Energy Network Operation Centre' platform, which provides technological assistance.
In the statement, the company did not disclose any financial details of the project.
According to industry estimates, to set up every 1 MW of solar capacity, an investment of over ₹4.5 crore is required.
AGEL has a total of 20.4 GW of renewable energy portfolio which includes the operational ones, under-construction, awarded and assets under acquisition catering to investment-grade counterparties.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.