Declaration of COD of Unit # 4 of Parbati-III HE Project, (4 x 130 MW), Himachal Pradesh

NHPC Ltd has informed BSE that consequent upon successful trial run of unit # 4 of Parbati-III power station (4x130 MW) at its maximum continuous rating of 130 MW for 12 hours on June 03, 2014, Unit # 4 is hereby declared under commercial operation w.e.f. 00:00 hrs of June 06, 2014.

Source : BSE - >www.bseindia.com

Published on June 05, 2014