Synchronisation of 300 MW Haldia Unit

| Updated on January 14, 2015 Published on January 14, 2015

CESC Ltd has informed BSE that the first 300 MW Thermal Power Unit of 2 x 300MW project at Haldia, West Bengal being executed by Haldia Energy Limited, a 100% CESC subsidiary, has been synchronized and the power generated at the station is now flowing to Kolkata through a 84km long transmission line.

Source : BSE - >www.bseindia.com