Mobility paves Samsung’s silver path
The Korean giant’s early bet on mobile phones helped it hit the $10-bn mark in India, but in its 25th year it ...
Construction works in progress Vallarpadam Intenational Conatainer Transshipment Terminal (ICTT) in Kochi,Kerala. Cochin Port Trust was first Indian Port to implement the revised manning scale. The first phase of the International Container Transshipment Terminal (ICTT) is scheduled to be operational shortly. The various projects taken up by the Cochin Port under the National Maritime Development Plan are progressing as per schedule. The quay-side cranes are expected to be delivered by 22nd May 2010. The connectivity to the ICTT got a shot in the arm with the successful trial run of locomotive on the rail route connecting Vallarpadam to Edapally. This rail route runs over the longest railway bridge in India measuring 4.6 kms. The two-lane National Highway Connectivity to the ICTT would be ready by May 2010. - Digital Picture By K K Mustafah - The Hindu Business Line
Indian ports, which handled about 560 million tonnes of cargo last fiscal, will be required to handle a throughput of 1,600 million tonnes by 2025-26, as per Government estimates. Independent forecasts peg the capacity requirement at a higher level of 3,000 million tonnes by 2020. But is the Indian port sector adding capacity at a pace matching the demand? Sadly, no.
Even though expansion is taking place, the pace is relatively tardy due to a variety of factors. The National Maritime Development Programme has laid out ambitious plans for development of ports, but a significant part of the proposals are yet to take off.
Under the programme, 276 projects were proposed up to 2011-12, envisaging an investment of Rs 1,00,339 crore based on 2004-05 prices. Of this Rs 55,804 crore is for the port sector and the rest for shipping and inland water transport sectors. But, out of the 276 projects, about 55-odd projects involving a capacity of about 70 million tonnes are complete, while about 80 other projects are under implementation. Thus, a bulk of the proposed projects, even after some 25 were subsequently dropped, is yet to take off.
Even a Parliamentary Committee on Estimates in its recent report has noted “with dismay” that the Government has not been able to create adequate capacity. “The committee fails to understand as to why not even 25 per cent of the targeted projects could not be achieved under the NMDP,” the report points out.
Analysts feel that a bulk of the projects will not be able to meet the 2011-12 deadline and will have to be carried forward to the subsequent Plan Periods. Several major projects have missed the deadline —for instance, the second chemical berth of Pir Pau, Mumbai, was originally scheduled for completion by March last year, but it may not be operational before mid-2012.
INFRASTRUCTURE
International norms have it that a gap of at least 30 per cent should be maintained between installed capacity and actual throughput. But the gap is about 8 per cent in the Indian ports sector, which is leading to substantial increase in waiting time for ships and a strain on the infrastructure, including cargo handling equipment.
Even though Indian ports have improved in terms of different productivity parameters, the existing levels are significantly below those of most of the world's biggest ports.
The Parliamentary Committee, in its report, has pointed out that the average turnaround time had improved from 10.10 days in 1990-91 to about 3.85 days in 2008-09. But, still the domestic port sector needs to cover significant grounds in shortening the turnaround time through improved cargo handling technology. For instance, the average turnaround time at Hong Kong port, which handles only container traffic, is 10 hours.
One of the biggest problems facing Indian ports is draft — inadequate draft prevents some of the ports from handling bigger ships.
While the State-owned Dredging Corporation of India (DCI) has not been able to add the required capacity, even most of the ports do not have adequate dredging capabilities. And this is paving the way for foreign dredging companies to take up a significant portion of the domestic dredging works.
The Parliamentary Committee feels that ideally DCI should have 1.5 times more capacity than the actual requirement so as to accommodate breakdown or maintenance of dredgers.
PRIVATE PARTICIPATION
One positive development has been the increased participation by private players in the ports sector. Last fiscal, about 13 PPP projects have been awarded, involving an investment of Rs 2,653 crore and a capacity of 65 million tonnes.
These include the mechanised coal handling facility at the general cargo berth at Visakhapatnam port and setting up of mechanised iron ore handing facilities at New Mangalore port.
Clearly, given the current trade growth rate, the domestic ports sector should hasten the process of capacity addition in order to meet the requirement in the next decade.
The Korean giant’s early bet on mobile phones helped it hit the $10-bn mark in India, but in its 25th year it ...
Antrix should adopt a different tactic than merely fighting over jurisdiction: Experts
Invest in relationships, enterprise, behaviour, effort and learning
From different types of osmoses to new membranes, researchers have come up with ways of drawing water
Will a stock continue its current trend or will it reverse? We tell you how you can read chart patterns to ...
Sensex and Nifty 50 saw selling interest on Friday and slumped; selling pressure could continue
Investors with a long-term horizon can consider this offer
Most AMCs have been sending out cryptic e-mails. We tell you how to read between the lines
In these isolated times when people yearn for a slice of the familiar, amateur and professional chefs are ...
On the eve of his 86th birthday, a peek into an interview-based book that reveals the actor’s many moods, ...
Forget the tuna. The island nation will keep you full and happy with coconut, koftas and jasmine
This year, on Facebook, I saw that someone had posted a list of EASY RESOLUTIONS. I didn’t copy them down but ...
Digital is becoming dominant media, but are companies and their ad agencies transforming fast enough to make a ...
Slow Network, promoted by journalist-lyricist Neelesh Misra, pushes rural products and experiences
How marketers can use the traditional exchange of festive wishes meaningfully
For Fortune, a brand celebrating its 20th anniversary, it was a rude shock to become the butt of social media ...
Three years after its inception, compliance with GST procedures remains a headache for exporters, job workers ...
Corporate social responsibility (CSR) initiatives of companies are altering the prospects for wooden toys of ...
Aequs Aerospace to create space for large-scale manufacture of toys at Koppal
And it has every reason to smile. Covid-19 has triggered a consumer shift towards branded products as ...
Please Email the Editor