Chief Minister Arvind Kejriwal is expected to inaugurate the national capital's first smog tower at Connaught Place on August 23, Delhi government officials said on Friday.

The construction of the smog tower has been completed and the inauguration will happen on August 23 instead of August 15, an official said requesting anonymity.

The over 20-metre-tall structure, being set up to improve air quality in a radius of around one km, was supposed to be ready by June 15.

Environment Minister Gopal Rai had earlier said the Covid-19 pandemic delayed the construction work of the smog tower.

The Delhi cabinet had approved the pilot project in October last year.

The smog tower will be able to purify 1,000 cubic metres of air per second, according to Rai.

A two-year pilot study will be undertaken to ascertain the effectiveness of the smog tower after it becomes operational, the official quoted above said.

Another 25-metre-tall smog tower, built by the Central government at Anand Vihar, is expected to become operational by August 31, officials of the Central Pollution Control Board said.

Project details

Tata Projects Limited (TPL) is building the two smog towers with technical support from IIT-Bombay, which, in collaboration with IIT-Delhi, will validate their performance.

NBCC India Ltd. has been appointed as project management consultant.

CPCB is the nodal agency for the tower at Anand Vihar, while Delhi Pollution Control Committe is the nodal agency for the one coming up at Connaught Place.

The two towers will have 1,200 air filters, each developed by experts at the University of Minnesota in the United States — which also helped design a 100-metre-high smog tower in Xian, China.

The smog towers, being built at a cost of ₹22 crore each, are estimated to reduce concentration of PM 2.5 up to 70 per cent in a one-km radius around them.

The Supreme Court had in January last year directed the central government to construct a smog tower to reduce pollution at Anand Vihar and the Delhi government to install another such structure at Connaught Place in three months.

In August, the apex court had reprimanded the Centre and State government for missing the deadline in completing the construction.