5.6 lakh housing units worth Rs 4.51 lakh cr facing delays in 7 major cities: Anarock

PTI New Delhi | Updated on April 09, 2019 Published on April 09, 2019

File photo   -  M Karunakaran

Every delayed project results in cost overruns which compound the funding crunch even further

Around 5.6 lakh housing units, worth Rs 4.5 lakh crore in seven major cities are running behind the delivery timelines mainly due to demand slowdown and fund diversion by developers, according to property consultant Anarock.

These 5.6 lakh flats were launched before 2013 in these seven cities -- National Capital Region (NCR), Mumbai Metropolitan Region (MMR), Chennai, Kolkata, Bengaluru, Hyderabad and Pune.

“The top 7 cities currently have a total stock of 5.6 lakh delayed housing units worth a whopping Rs 4,51,750 crore,” Anarock founder and chairman Anuj Puri said.

“Lakhs of buyers across top cities — particularly MMR and NCR - have been left in limbo, leading to inconceivable mental stress and financial pain,” he added.

As per the Anarock data, the NCR and MMR account for 72 per cent of the total stuck housing units.

In MMR, as many as 1,92,100 apartments worth Rs 2,17,550 crore are delayed, while the NCR has 2,10,200 units worth Rs 1,31,460 crore running behind the schedule.

The main southern cities of Bengaluru, Chennai and Hyderabad together account for a mere 10 per cent of the overall stuck housing units of a total worth of Rs 41,770 crore. The Southern cities have predominantly been driven by service-class end-users, leaving limited scope for developers to be unprofessional.

“It has become a ‘chicken and egg’ situation - buyers have understandably stopped releasing funds to builders, and builders claim they have no funds to complete construction,” he added.

Every delayed project results in cost overruns which compound the funding crunch even further.

Anarock chairman said the lack of project clearances for whatever reason also contributes to the piling up of housing stock. In the pre-RERA era, many builders launched greenfield projects without the requisite approvals in place, resulting in their projects getting stuck.

The consultant said that by amending the Insolvency and Bankruptcy Code (IBC) and treating buyers at par with banks and other creditors, the government has safeguarded the interests of affected buyers.

“Whichever government is in power after the upcoming general elections, it has a mammoth task to complete. Delayed projects have severely weakened faith in under-construction properties and reviving buyers’ trust is a herculean task,” Puri said.

If buyers stop purchasing under-construction properties, builders would have a far more challenging time to get funds from external sources for project construction, he added.

Published on April 09, 2019

A letter from the Editor


Dear Readers,

The coronavirus crisis has changed the world completely in the last few months. All of us have been locked into our homes, economic activity has come to a near standstill. Everyone has been impacted.

Including your favourite business and financial newspaper. Our printing and distribution chains have been severely disrupted across the country, leaving readers without access to newspapers. Newspaper delivery agents have also been unable to service their customers because of multiple restrictions.

In these difficult times, we, at BusinessLine have been working continuously every day so that you are informed about all the developments – whether on the pandemic, on policy responses, or the impact on the world of business and finance. Our team has been working round the clock to keep track of developments so that you – the reader – gets accurate information and actionable insights so that you can protect your jobs, businesses, finances and investments.

We are trying our best to ensure the newspaper reaches your hands every day. We have also ensured that even if your paper is not delivered, you can access BusinessLine in the e-paper format – just as it appears in print. Our website and apps too, are updated every minute, so that you can access the information you want anywhere, anytime.

But all this comes at a heavy cost. As you are aware, the lockdowns have wiped out almost all our entire revenue stream. Sustaining our quality journalism has become extremely challenging. That we have managed so far is thanks to your support. I thank all our subscribers – print and digital – for your support.

I appeal to all or readers to help us navigate these challenging times and help sustain one of the truly independent and credible voices in the world of Indian journalism. Doing so is easy. You can help us enormously simply by subscribing to our digital or e-paper editions. We offer several affordable subscription plans for our website, which includes Portfolio, our investment advisory section that offers rich investment advice from our highly qualified, in-house Research Bureau, the only such team in the Indian newspaper industry.

A little help from you can make a huge difference to the cause of quality journalism!

Support Quality Journalism
This article is closed for comments.
Please Email the Editor
You have read 1 out of 3 free articles for this week. For full access, please subscribe and get unlimited access to all sections.