Kudankulam project first unit may begin commercial operations by May

PTI Updated - March 12, 2018 at 12:51 PM.

Hit by protests, commissioning of the first unit of the Indo-Russian Kudankulam Nuclear Power Project has been further delayed by another two months to May next.

After achieving 99.2 per cent of the physical progress to produce 1,000 MW of power, the first unit is now expected to go for commercial operations by May next year, Nuclear Power Corporation of India Ltd said.

The plant was earlier scheduled for commercial operations in December but it was deferred to March next due to the stir by locals and resultant stand-off between them and government.

Commercial operations of the second unit to produce another 1,000 MW is now expected by Feb 2013, the company said.

The project is dogged by controversy with locals raising safety concerns and persisting with protests despite a government appointed experts panel vouching for its safety.

The third round of talks with the central experts panel to break the impasse failed to make headway yesterday with the protesters saying that the safety concerns were not addressed.

Meanwhile, shops in Idinthakarai and Kudankulam in Tirunelveli district remained closed with black flags fluttering atop houses, to protest the proposal for construction of two more reactors of Russian design.

The protest coincides with the three-day visit of the Prime Minister, Dr Manmohan Singh, to Russia from yesterday but the contract for construction of two more reactors of Russian design at Kudankulam is unlikely to be signed even though negotiations are at an “advanced” stage.

Besides those observing fast as part of the third phase of agitation at Idinthakarai for the 60th day today, another section of fishermen began a 72-hour fast and boycott of fishing to protest building two more plants at Kudankulam.

Meanwhile, People’s Movement Against Nuclear Energy, spearheading the stir, said the next round of talks with the Central Government Expert Committee would be possible only if the government provided 14 documents sought by them.

The documents sought included reports and comments from the Ministry of Environment and Forests, minutes of all meetings of the Expert Appraisal Committee of the MoEF and supplementary or additional reports/studies submitted to MoEF pursuant to any queries of the EAC on both reactors, the movement convenor, Mr N. Pushparayan, who represented the state committee during talks with the central panel, said.

Published on December 16, 2011 09:30