As many as 377 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns of more than Rs 3.94 lakh crore owing to delays and other reasons, according to a report.
The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above.
Of such 1,635 projects, 377 projects reported cost overruns and 565 projects time escalation.
“Total original cost of implementation of the 1635 projects was Rs 19,47,462.67 crore and their anticipated completion cost is likely to be Rs 23,41,784.84 crore, which reflects overall cost overruns of Rs 3,94,322.17 crore (20.25 per cent of original cost),” the ministry’s latest report for September 2019 said.
According to the report, the expenditure incurred on these projects till September 2019 was Rs 9,96,613.94 crore, or 42.55 per cent of the anticipated cost of the projects.
However, it said the number of delayed projects decreases to 495 if delay is calculated on the basis of the latest schedule of completion.
Further, it said that for 693 projects neither the year of commissioning nor the tentative gestation period has been reported.
Out of 565 delayed projects, 182 projects have overall delay in the range of 1 to 12 months, 129 projects 13 to 24 months, 140 projects reflect delay in the range of 25 to 60 months and 114 projects show delay of 61 months and above.
The average time overrun in these 565 delayed projects is 38.41 months.
The brief reasons for time overruns, as reported by various project implementing agencies, are delays in land acquisition, forest clearance and supply of equipment.
Besides, there are other reasons like fund constraints, geological surprises, geo-mining conditions, slow progress in civil works, shortage of labour, inadequate mobilisation by the contractor, Maoist problems, court cases, contractual issues, ROU/ROW (right of use/right of way) problems, law and order situation, among others, the report said.
It also observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported.
The Korean giant’s early bet on mobile phones helped it hit the $10-bn mark in India, but in its 25th year it ...
Antrix should adopt a different tactic than merely fighting over jurisdiction: Experts
Invest in relationships, enterprise, behaviour, effort and learning
From different types of osmoses to new membranes, researchers have come up with ways of drawing water
High valuation and stiff competition from larger players are a dampener
₹1503 • HDFC Bank S1S2R1R2COMMENT 1500148015101525 As the stock has broken out of resistance at ₹1,500, ...
The stock of Kajaria Ceramics Limited, after witnessing a fresh breakout, on Tuesday hit a fresh 52-week high ...
Will a stock continue its current trend or will it reverse? We tell you how you can read chart patterns to ...
In these isolated times when people yearn for a slice of the familiar, amateur and professional chefs are ...
Writer Narendra’s latest book, rich with vignettes from Bastar and his native village in Uttar Pradesh, ...
On the eve of his 86th birthday, a peek into an interview-based book that reveals the actor’s many moods, ...
Forget the tuna. The island nation will keep you full and happy with coconut, koftas and jasmine
Digital is becoming dominant media, but are companies and their ad agencies transforming fast enough to make a ...
Slow Network, promoted by journalist-lyricist Neelesh Misra, pushes rural products and experiences
How marketers can use the traditional exchange of festive wishes meaningfully
For Fortune, a brand celebrating its 20th anniversary, it was a rude shock to become the butt of social media ...
Three years after its inception, compliance with GST procedures remains a headache for exporters, job workers ...
Corporate social responsibility (CSR) initiatives of companies are altering the prospects for wooden toys of ...
Aequs Aerospace to create space for large-scale manufacture of toys at Koppal
And it has every reason to smile. Covid-19 has triggered a consumer shift towards branded products as ...
Please Email the Editor