Solar is not cheap everywhere and this is what Neyveli Lignite Corporation has learnt.
The public sector ‘navratna’ company floated a tender for turnkey contract for building 250 MW of solar projects in Odisha, but the entire programme is in danger of getting scrapped.
Two categoriesThe tender asked bidders to name their prices under two categories — using only locally made cells and modules, with ‘viability gap funding’ from government of India, and in the ‘open’ category. In the open category, the project could use imported cells and panels, which are cheaper.
Only two companies bid in the open category – Vikram Solar, which quoted a price of ₹5.46 crore a MW, and Jakson Solar, which quoted ₹5.50 crore. In contrast, in another recent tender for 500 MW projects in Tamil Nadu, the least bidder, Gamesa, had quoted ₹4.34 crore.
NLC’s Chairman and Managing Director confirmed this and said that the rates were too high.
In the ‘domestic content requirement’ category, only three companies showed interest – Adani (₹5.73 crore), Vikram Solar (₹6.26 crore) and Jakson (₹7.15 crore). But for any of these bids to be awarded here, the government of India has to sanction viability gap funding. Acharya noted that VGF was not forthcoming from the government.
The situation is thus that the DCR quotes cannot be taken unless GoI grants VGF, while open category quotes are too high.
Sources in NLC said that it might ask the two bidders to further bid against each other and lower the prices. However, industry sources said that such a ‘reverse bidding’ could not be done if there are only two bidders, as per the tender conditions.
Comments
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of TheHindu Businessline and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.