L&T secures extension of repayment deadline from lenders for Hyderabad metro project

V Rishi Kumar Hyderabad | Updated on September 10, 2018 Published on September 10, 2018

In talks with State on project cost escalation

With the Hyderabad metro rail project poised for completion by March 2019, a year and a half after the initial programmed schedule of July 2017, the lenders have given construction major L&T more time for commercial operation up to July 2019, with a corresponding increase in loan period.

As per the revised schedule, the metro rail project, being implemented by concessionaire L&T, the loan repayment will start from September 30, 2020.

However, the corresponding cost implication due to delays in securing right of way to implement the project is being assessed for claiming compensation, according to L&T's annual statement to its shareholders.

The ₹16,375-crore elevated metro rail project under implementation covers 72 km rail and 6 million sq ft of transit oriented development. This is being funded by a term loan of ₹11,478 crore, equity share capital of ₹3,439 crore and a Viability Gap Fund from the government of ₹1,458 crore.

In addition, the State government has invested more than ₹2,000 crore in facilitating construction and right of way.

Investment, VGF

L&T has as of March 2018, invested ₹14,723 crore in the project, including ₹2,241 crore during 2017-18. While a 30-km stretch was commissioned in November 2017 by the Prime Minister Narendra Modi, two other stretches, which will mark the completion of two of the three corridors, are expected to be commissioned by September and October-November. The other stretch minus the Old City segment, where there are right of way challenges, will be ready by March-April 2019.

Referring to the Transit-Oriented Development, L&T stated that commercial, operations at two locations including at the IT hub of Hitec city have commenced, and at two other locations are close to completion.

Efforts are on to develop a couple of other locations.

The metro concessionaire is exploring non-fare revenue generation through cross selling of products to commuters. This is seen to further get strengthened by metro expansion, which will result in higher ridership.

The Telangana government has plans to implement phase II of the metro project, covering 85 km, including providing an airport link. This will enhance the average ridership on the metro system significantly.

Outlook

Providing its outlook for metro, L&T states that once two corridors get fully commissioned during the calendar year, its operations would span 56 km and expand the ridership to about 6.15 lakh per day. Recently, the metro ridership crossed 20 million since its commissioning in November 2017.

The metro concessionaire has tied up with a solar power developer for 10 MW for captive use.

L&T is also exploring the possibility of offering consultancy services to other metros.

Published on September 10, 2018

A letter from the Editor


Dear Readers,

The coronavirus crisis has changed the world completely in the last few months. All of us have been locked into our homes, economic activity has come to a near standstill. Everyone has been impacted.

Including your favourite business and financial newspaper. Our printing and distribution chains have been severely disrupted across the country, leaving readers without access to newspapers. Newspaper delivery agents have also been unable to service their customers because of multiple restrictions.

In these difficult times, we, at BusinessLine have been working continuously every day so that you are informed about all the developments – whether on the pandemic, on policy responses, or the impact on the world of business and finance. Our team has been working round the clock to keep track of developments so that you – the reader – gets accurate information and actionable insights so that you can protect your jobs, businesses, finances and investments.

We are trying our best to ensure the newspaper reaches your hands every day. We have also ensured that even if your paper is not delivered, you can access BusinessLine in the e-paper format – just as it appears in print. Our website and apps too, are updated every minute, so that you can access the information you want anywhere, anytime.

But all this comes at a heavy cost. As you are aware, the lockdowns have wiped out almost all our entire revenue stream. Sustaining our quality journalism has become extremely challenging. That we have managed so far is thanks to your support. I thank all our subscribers – print and digital – for your support.

I appeal to all or readers to help us navigate these challenging times and help sustain one of the truly independent and credible voices in the world of Indian journalism. Doing so is easy. You can help us enormously simply by subscribing to our digital or e-paper editions. We offer several affordable subscription plans for our website, which includes Portfolio, our investment advisory section that offers rich investment advice from our highly qualified, in-house Research Bureau, the only such team in the Indian newspaper industry.

A little help from you can make a huge difference to the cause of quality journalism!

Support Quality Journalism
This article is closed for comments.
Please Email the Editor
You have read 1 out of 3 free articles for this week. For full access, please subscribe and get unlimited access to all sections.