Pampa Action Plan hits roadblock

G.K. Nair

Clubbing of Sabarimala projects with PAP puts hurdles in river cleansing work


Most of the projects under the first phase of PAP have to be implemented by the TDB.

Kochi , June 13

The clubbing of Sabarimala development projects with those under the Pampa Action Plan (PAP) is understood to have blocked the latter following a dispute between the Travancore Devaswom Board (TDB) and the forest department.

Since the first phase of the PAP projects to be implemented in Sabarimala and Pampa have been approved by the Union Ministry of Environment and Forests (MoEF) already, there would not be any objection from the forest department to its implementation.

Besides, there is no dispute over the additional forestland of 2.44 hectare required for these projects, according to Mr N.K. Sukumaran Nair, General Secretary, Pampa Parirakshana Samithi.

Most of the projects under the first phase of PAP have to be implemented by the TDB, which clubbed the Sabarimala projects with it and that has blocked its implementation now, he alleged.

The Samithi, in a bid to get the hurdles removed, had recently apprised the Kerala Minister for Water Resources, Mr N.K. Premachandran, of the importance of implementing the PAP and the Minister had agreed to look into the issues involved, Mr Nair told Business Line.

`Misconception'

He said that there was a misconception that the PAP was for the development of Sabarimala. The Centre under the National River Conservation Programme (NRCP) had approved cleansing of the Pampa river, which gets heavily polluted during the Sabarimala pilgrimage season every year, so as to provide safe water to around 40 lakh people living in the river basin, he said.

In fact, the importance of this phenomenon has been overlooked by the wrong belief, he said. The MoEF has approved the first phase of the PAP considering the seriousness of the problem and the need to keep the Pampa river clean, as during the pilgrimage season coliform bacteria in the river was found to be very high — three lakh per 100 ml, he said.

"This indicates the high level of sewage pollution in the river due to the absence of sufficient sanitary facilities at Sabarimala, Pampa and towns en route for pilgrims and the public in the nearby inhabitations," Kerala State Pollution Control Board (PCB) pointed out.

The water quality monitoring of the Pampa river was done by the PCB on the directions of the Kerala High Court.

implementation problems

The MoEF had approved the PAP and included Pampa in the NRCP in 2001 and later accepted the Rs 319.70-crore project, submitted by the State Government on December 19, 2002, to be completed in three phases.

Subsequently, for the implementation of the first component of the project — involving a total investment of Rs 18.45 crore, the NRC Directorate had sanctioned its 70 per cent share of the cost (Rs 12.91 crore) in June 2003.

Besides, a sum of Rs 75 lakh was also given as advance. "But the State Government has so far not done anything towards implementing the PAP," Mr Nair said.

The previous State Cabinet had taken a decision to set up a Pampa River Basin Development Authority in December 2004. Besides, a Steering Committee was also constituted.

The Centre had also issued guidelines for the implementation of the PAP and as per the approval procedure set by the MoEF for the Ganga Action Plan, approval of river action plans is accorded by the government on the basis of pre-feasibility report estimates prepared by the state governments.

After the scheme is approved, detailed project reports (DPR) with firmed-up cost estimates for various sub-components are prepared by the state governments. These DPRs are appraised and approved by the Ministry following which administrative approval and expenditure sanctions are issued.

The progress is monitored by both the State or implementing agencies and the Ministry.

But none of these procedures has so far been followed by the authorities here, Mr Nair alleged.

More Stories on : Infrastructure | Water | Environment | Kerala

Article E-Mail :: Comment :: Syndication :: Printer Friendly Page



Stories in this Section
UTI MF devises overseas fund `Desh Videsh'


Cabinet refers LNG duty revision issue to GoM
`Japanese cos to step up investments in India'
Lanka wants SSIs to be included in FTA
`HSIDC, Reliance to sign pact on June 19'
Pampa Action Plan hits roadblock
Gujarat employs contractors to complete dam canal
Srei Infrastructure bags Rs 3,000-cr road projects
Left demands rollback in fuel price hike
Delhi Govt waives VAT on petrol, diesel price hike
IndianOil to implement Panipat-Jalandhar pipeline
Coal mine allotment to 28 PSUs soon
AP tops in power sector performance
`Energy service cos can play vital role in efficiency'
Ratnagiri project running short of naphtha
TN looks at revenue mop-up on tax deferral schemes
Tyre makers to move Finance Ministry
MNJI & RCC to be developed
Fan makers get orders from Colombo, Dubai
Residential rentals in Chennai go up
Metal Box sells Faridabad property to Lakhani
Condor group plans mall and multiplex
Picking up the resettlement gauntlet
6th Pay Commission to be set up soon
Global Leaders summit in Nov
APSFC plans schemes for entrepreneurs
Textile exports to US — Weaving success, post-quotas
Value-based tea export strategy required
Wheat tender bypasses Plant Quarantine Order
Seminar on exports from coastal Karnataka


The Hindu Group: Home | About Us | Copyright | Archives | Contacts | Subscription
Group Sites: The Hindu | Business Line | Sportstar | Frontline | The Hindu eBooks | The Hindu Images | Home |

Copyright © 2006, The Hindu Business Line. Republication or redissemination of the contents of this screen are expressly prohibited without the written consent of The Hindu Business Line